NEW CONSTRUCTION
BENAROYA BUILDING
Roofing
System Installed:
For this project, a Fields HAI-X35-MS 4 sheet system was installed,
with T3 hot Asphalt. This installation consists of an approved 3-ply
insulation of F54 and a F58 glass cap.
Challenges:
Turnaround time was critical. Completing the project by the date
required was the most important challenge of this project.
Solutions:
In order to accommodate the tight turnaround, ROOFCORP
purchased a "Mother Tank" with the capacity to hold 37 Asphalt tons
and scheduled 2 crews of about 25 people each day.
Size:
390,000 Sf
Added
Value:
Completed the project early so that other trades could go to work
inside the building.
|