NEW CONSTRUCTION
BEAR CREEK SCHOOL
Roofing
System Installed:
ROOFCORP
installed a mechanically attached Carlisle TPO system on the low
slope portion of the building. The steep slope roofs consisted of
a 30 years composition shingles as manufactured by PABCO.
Challenge:
When ROOFCORP
started this project, winter was at its peak. The reduced daylight
hours reduced the number of workable hours under normal conditions.
Solution:
In order to improve working conditions, and extend workable hours,
floodlights were dedicated for each crew at the job sight.
Size:
45,000 SF
Added Value:
By controlling external variables such as bringing an additional
lighting to increase the number of workable hours per day ROOFCORP
is capable of providing exceptional turnaround time all year long.
This particular project was completed in under 30 days, exceptional
for a project of this scope done at this time of year.
|