NEW CONSTRUCTION
SAFEWAY YELM
Roofing
System Installed:
ROOFCORP installed a torch down (US Intec) system (LCSP 2 BRI) was
applied with a 12 year NDL warranty.
Challenge:
Due to the customer's scheduling requirements, the deadline for
completion of this job was unusually short -under a week.
Solution:
ROOFCORP increased the number of crew members (24 workers/day) and
resources at the job site and completed the roof in an amazing two-and-a-half
days.
Size:
54,500SF
Added Value:
ROOFCORP has the ability to significantly increase or reduce the
number of crews working on a specific job, depending on the need.
If specific tasks require special efficiency, more crews can be
sent for that task and withdrawn when finished.
|